Sabine Pass Liquefaction Expansion (Stage 5), Cameron Parish

LNG export terminal expansion · Cameron Parish, Louisiana Very large and still early

Evidence through Nov 24, 2026 · first published Nov 27, 2026 · last material update Nov 27, 2026

Cheniere plans to add up to three liquefaction trains, up to about 20 mtpa in total, at its Sabine Pass LNG Terminal in Cameron Parish, Louisiana. Phase 1 is Train 7 (over 6 mtpa) plus a boil-off gas re-liquefaction unit; a lump-sum turnkey EPC for Phase 1 was signed with Bechtel in May 2026 under a limited notice to proceed, with FID expected by early 2027. Press reports say the federal siting authorization for Trains 7 to 9 came in November 2026, and later that month Cheniere asked for approval to start early site work. A separate October 2026 state jobs-incentive application listing $15 billion names no project, so its tie to this expansion is an inference.

Owner
Sabine Pass Liquefaction Stage V, LLC (part of Cheniere Energy Partners, L.P. (Cheniere Energy, Inc.)) (confirmed from the record)
Location
Cameron Parish, Louisiana
Project type
LNG export terminal expansion
Scope
Up to three new large-scale liquefaction trains at the existing Sabine Pass LNG Terminal, built in phases; Phase 1 is Train 7, a boil-off gas re-liquefaction unit, supporting infrastructure and tie-ins to the existing terminal.
Size
Up to about 20 mtpa peak for the full expansion including debottlenecking; Phase 1 (Train 7) more than 6 mtpa
Estimated value
$15 billion (estimated investment on a Cheniere operations entity's state jobs-incentive application, Oct 2026; the filing names no project, so the link to this expansion is inferred and is not a confirmed project cost)[1]
Regulatory status
Federal siting authorization granted (per press reports); export approval pending · Nov 19, 2026
Press reports say the federal natural gas siting authorization for Trains 7, 8 and 9, the Sabine Crossing Pipeline and the Creole Trail expansion was granted unanimously, with 10 years to complete construction. The order itself was not reviewed. Federal approval to export to non-free-trade-agreement countries was still pending.
[2]
Commercial stage
Main contractor (EPC) chosen
Phase 1 only: Sabine Pass Liquefaction Stage V, LLC signed a lump-sum turnkey EPC with Bechtel Energy, Inc. covering Train 7, a boil-off gas re-liquefaction unit, supporting infrastructure and tie-ins, with a limited notice to proceed releasing early engineering and procurement. No price is disclosed and FID on Phase 1 is expected by early 2027. Phase 2 (Trains 8 and 9) has no FID or EPC award.
[3]

Where the public evidence puts the project today. Permit approvals and commercial decisions are tracked separately below.

Track this project. Get an alert when a new filing, approval or milestone shows up, with the original records, the companies involved and who to contact.

Track this project Find similar projects in Louisiana

Milestones

DateWhatKindStatus
Feb 2025Cheniere targets expansion FID in late 2026 or 2027[4]CommercialHappened
May 2026Lump-sum turnkey EPC for Phase 1 signed with Bechtel; limited notice to proceed issued[5]CommercialHappened
Oct 29, 2026State jobs-incentive application listing $15B investment on state board agenda (filing names no project)[1]Permits and approvalsHappened
Nov 19, 2026Federal siting authorization for Trains 7, 8 and 9 (per press reports)[2]Permits and approvalsHappened
Nov 2026Cheniere requests federal approval for early site work[6]Permits and approvalsHappened
Early 2027 (target)Phase 1 (Train 7) final investment decision[3]CommercialTarget date
Date not givenFederal approval to export to non-free-trade-agreement countries[2]Permits and approvalsNot established
Date not givenPhase 2 (Trains 8 and 9) FID and EPC award[7]CommercialNot established

A target date is what a source said was planned, not proof it happened.

Equipment

Named in a source

  • Liquefaction Train 7 · Phase 1 train of more than 6 mtpa including debottlenecking, in Bechtel's lump-sum turnkey EPC scope.[3]
  • Boil-off gas re-liquefaction unit · Part of Phase 1 scope alongside supporting infrastructure and tie-ins to the existing terminal.[3]
  • Tie-ins to existing LNG storage tanks · Both phases describe tie-ins to the terminal's five existing LNG tanks; no new LNG tanks are described.[8]
  • Ground flare, three new BOG compressors, dual-berth loading · Listed in Phase 2 (Trains 8 and 9, about 6 mtpa each) scope; no FID or EPC award.[7]
  • Tarpon Compressor Station, 52,500 HP · Associated Creole Trail pipeline expansion compression in Cameron Parish; no vendor or driver type stated.[9]

Possibly relevant

  • Shop-fabricated pressure vessels · A liquefaction train and BOG re-liquefaction unit need many separators, drums and columns; would sit in Bechtel's scope.
  • Refrigerant or NGL storage spheres/bullets · Liquefaction trains typically store refrigerant make-up; scope for Train 7 is not stated.
  • Atmospheric, firewater and utility water tanks · Phase 1 includes supporting infrastructure and utilities; no tank list found.
  • Gas turbine inlet cooling · Relevant if Train 7 uses gas turbine drivers; driver type not found.
  • Heat exchangers and amine treating unit · Typical for each liquefaction train's pretreatment and cooling.
  • Transformers and E-houses · Typical power distribution for a new train and utilities.
  • Cryogenic pumps and valves · Typical for LNG run-down and tie-ins to existing storage.

Typical for this kind of project. Not confirmed for this one.

What it means for suppliers

Our read: Bechtel is the buyer for Phase 1 and is already doing early engineering and procurement under its limited notice to proceed, so vessel, tank, compressor, electrical and instrumentation suppliers should be working Bechtel's bidder lists now, ahead of an FID expected by early 2027. New full-containment LNG tanks do not appear to be in scope, so tank makers should focus on smaller utility, firewater and refrigerant storage. Phase 2 (Trains 8 and 9) is a later, uncommitted opportunity with no EPC named.

Still unknown

Sources

  1. [1] Incentives and tax abatement · Public record · No. 20250454-QJ · Oct 29, 2026
  2. [2] www.newslinelocal.com · Published source
  3. [3] Government record · Public record
  4. [4] GEM wiki: Sabine Pass LNG Terminal · Published source
  5. [5] Government record · Public record
  6. [6] News report · News · trade_lngprime · Nov 24, 2026
  7. [7] CompressorTECH2: Cheniere seeks to expand Sabine Pass · Published source
  8. [8] Cheniere Sabine Pass page · Published source
  9. [9] Government record · Public record

Government records are described by kind, number and date. Members open the original record for every filing in the app.

Reviewed by the Industrial OpAtlas editor before publication. Found something wrong or out of date? Send a correction.

Cite this page: Industrial OpAtlas, "Sabine Pass Liquefaction Expansion (Stage 5), Cameron Parish", Nov 27, 2026, https://industrialopatlas.com/projects/1022-sabine-pass-liquefaction-expansion-stage-5-cameron-parish-la